Akufo-Addo commissions 330kv Kumasi-Bolgatanga power transmission project

The project was financed by the French Development Agency (AFD) at a total cost of US$173.9 million

President Nana Addo Dankwa Akufo-Addo has commissioned the 330 kilovolt Kumasi to Bolgatanga Transmission Line Project, at the commencement of his four-day tour of the Ashanti Region.

The project, which is an integral part of the West Africa Power Pool Project, seeks to reinforce the Ghana Transmission System, and ensure the export of at least 100 megawatts of electricity to Burkina Faso, as well as increase the reliability of the Ghana to Burkina Interconnection Project.

To help achieve this objective, GRIDCo also constructed a 330kV Transmission line from the Aboadze Power Generation enclave through Prestea to Kumasi.

The 330kv Kumasi-Bolgatanga power transmission project
The 330kv Kumasi-Bolgatanga power transmission project

The 330 kV Kumasi-Bolgatanga Transmission Line Project consisted of the construction of approximately 550km of 330kV Transmission Line from Kumasi to Bolgatanga, the construction of 330kV Substations at Kumasi, Kintampo, Tamale and Bolgatanga as well as expansions of the existing 161kV Substations at these locations, and the implementation of Environmental Mitigation Measures and a Resettlement Action Plan for the Project.

The project was financed by the French Development Agency (AFD) at a total cost of US$173.9 million.

Not only has the project succeeded in supplying 150 megawatts of power to Burkina Faso, but it has also increased transmission capacity to meet growing demand in Ashanti, northern Ghana and beyond.

The Minister for Energy, Matthew Opoku Prempeh, also noted that the projects have also contributed to the reduction of transmission line overloads and associated high transmission losses and improved voltages particularly in Ashanti, Bono and Bono East regions.

President Nana Akufo-Addo and other officials at the commissioning of the 330kv Kumasi-Bolgatanga power transmission project
President Nana Akufo-Addo and other officials at the commissioning of the 330kv Kumasi-Bolgatanga power transmission project

He stressed that the 330kV transmission lines have also helped to improve the quality and reliability of electricity supply in the country.

History of WAPP

The West Africa Power Pool projects commenced with the Coastal Transmission Backbone Projects (CTB) which involved the construction of 330kV Aboadze-Volta (Tema)-Momehagou (Togo) Transmission Line and associated substations as well as the upgrade of Power Generation facilities in Ghana.

The projects were jointly implemented by the Volta River Authority (VRA), Ghana Grid Company Limited (GRIDCo) and Communauté Electrique du Bénin (CEB) of Togo/Benin and completed in 2014.

The 330kv Kumasi-Bolgatanga power transmission project
The 330kv Kumasi-Bolgatanga power transmission project

The developmental objective of the CTB project was to increase access of WAPP “Zone A” coastal states (Cote-d’ivoire, Ghana, Togo, Benin & Nigeria) to more stable and reliable electricity to alleviate power supply deficits and to reduce their collective vulnerability to drought-induced power supply disruptions.

The subsequent project was the Interzonal Hub Transmission Project. The development objective of the first phase of the project was to reduce the cost of and improve security of electricity supply to Burkina, while increasing Ghana’s electricity export capacity.

Asaase Radio 99.5 broadcasts on radio via 99.5 in Accra, 98.5 in Kumasi, 99.7 in Tamale, 100.3 in Cape Coast and on our affiliates Bawku FM 101.5 in Bawku, Beats FM 99.9 in Bimbilla, Somua FM 89.9 in Gushegu, Stone City 90.7 in Ho, Mining City 89.5 in Tarkwa and Wale FM 106.9 in Walewale
Tune in or log on to broadcasts 
online: www.asaaseradio.com, Sound Garden and TuneIn
Follow us on Twitter: @asaaseradio995
Live streaming: facebook.com/asaaseradio99.5. Also on YouTube: Asaase Radio Official.
Join the conversation. Call: 020 000 9951 or 059 415 7777. Or WhatsApp: 020 000 0995.

#AsaaseRadio

Show More

Related Articles

Back to top button

Adblock Detected

ALLOW OUR ADS